Board columns (states)

The block Board columns (statuses) in Project settings defines the states a task of the project can have. Each state is also a column of the board. The order of the list is the order of the columns.

Set up a column​

  1. Press Add column at the top right of the block. A new row appears at the bottom.
  2. Choose the colour with the colour square at the start of the row; No color clears it.
  3. Type the name in the field Name…
  4. Choose the meaning in the list State meaning.
  5. Set the order with the arrows Move up and Move down; the cross Remove deletes the row.
  6. Press Save at the bottom of the tab.

Tasks stay in their column when you rename it. Every column needs a name before the settings can be saved.

The meaning of a state​

The list State meaning offers No meaning, In backlog, Ready to start, In progress, Completed and Cancelled. The meaning is a property of the state itself, so two projects can call their finished state differently. A task is closed when the meaning of its state is Completed or Cancelled; a state with an empty meaning is open.

The meaning is used in these places:

PlaceWhat it does with the meaning
Filter Not closedLists the tasks whose state is open.
Mark OverdueAppears on a task with a past due date whose state is open.
Recent tasks, links and subtasksA closed task is shown with a struck-through title.
Parents and subtasksA parent closes with its subtasks, see Subtasks and links.
Moving a task and importing tasksA state is matched to the state with the same meaning.

Card limit​

Under each column the row Card limit holds a number from 1 up to 9999 and a list Over the limit:

  • Only mark the column — the column accepts more cards, and its counter on the board turns to the warning colour;
  • Don't allow more cards — a full column refuses new cards.

The list is available once a number is set; an empty field removes the limit.

With the setting Don't allow more cards a full column refuses a card on every path that puts a task there: dragging on the board, the state in the card, the bulk bar, moving a task from another project. The refusal names the column and the limit. The automatic closing of a parent after its subtasks (see Subtasks and links) ignores the limit. The counter of the column on the board reads cards/limit.

What's next​