Selecting several tasks

With the right 管理任务 every row of the table and the list has a checkbox. Select several tasks and a bar appears above the list: one choice in it changes all selected tasks at once.

Select tasks​

  • Tick the checkbox (选择任务) of a task. Tick several.
  • Tick the checkbox in the table header (全选) to select every task shown; a partly ticked header shows that only some tasks are selected.
  • The selection is cleared when you switch the project, change the conditions, turn to another page or change the grouping. The button 取消选择 clears it too.

The bar starts with the line 已选择:…; the number of selected tasks stands in place of the ellipsis.

Change the selected tasks​

Control of the barWhat it does
状态Moves the selected tasks to the chosen state. Shown when all selected tasks belong to one project.
负责人Assigns the chosen person. The list holds the people who can be assigned to every selected task; it has a search field.
优先级Sets the chosen priority level.
类型Sets the type. Shown when the project has types.
The date field 截止日期 and 应用Sets the due date; Enter applies it too.
清除截止日期Removes the due date.
添加标签Adds a tag from the list.
The field 新标签…Adds a new tag with the name you type; press Enter.
移除标签Removes a tag that the selected tasks carry. Shown when they carry any.
附加字段Choose a custom field of the project, then its value, and press 应用 (a list or user field applies the chosen value at once).
删除Moves the selected tasks to the trash after the question 删除 … 个任务?您可以从回收站中恢复它们。 (the number of tasks stands in place of the ellipsis).
取消选择Clears the selection and leaves the tasks as they are.

A date has to fall between the years 1970 and 2105; otherwise the field says 截止日期的年份必须在 … 到 … 之间 (the two limits stand in place of the ellipses).

When some tasks stay as they are​

After a mixed result a message 已更改:…,被拒绝:…,未找到:… counts the tasks: changed, denied (they are outside the tasks you may change, or a rule refused them) and missing; the three numbers stand in place of the ellipses. It can add reasons, each as a tail of the same message (hence the comma at the start of each):

  • ,未保存:… — tasks whose saving failed (their number stands in place of the ellipsis);
  • , not changed — a required field would be left empty: … — tasks that stay as they are because a required field would be left empty (the numbers of the tasks are listed in place of the ellipsis);
  • , not changed — the column is full: … — tasks that stay as they are because the column of the new state is full (the numbers are listed in place of the ellipsis);
  • the text of a transition check that refused the change, with the numbers of the tasks it refused.

The rest of the selected tasks are changed.

In the list of all tasks​

The bar works over tasks of several projects. The controls that depend on a project (状态, 类型, project fields) appear when all selected tasks belong to one project; the priority list holds the levels common to all selected projects.

What's next​